How Do I Create Budgets?

See Also

 

With ArchiOffice, you can effectively manage projects by setting budgets for each phase of the project. Do the following to create a project budget:

  1. Click Projects on the navigation bar.
  2. Select a listed project to edit.
  3. On the Details tab, select Open from the Project Status drop-down list. Do this at the quote stage of a project, before it becomes active.
  4. Click the Phases/Codes tab.
  5. In the Budget Hrs field, set overall hourly budget for each phase.
  6. On the Projects -Billing screen, select Budgets from Action drop-down list on the button panel
  7. Set the phase fees.

On the Projects -Tasks screen, you can have an hourly budget calculated from the tasks. In this case, in phase 01 Pre-Design, the total of the individual tasks comes to 43.50 hours, well within the phase budget of 100 hours.

  1. Project budgets can be established for each phase either by specifying a percentage of a total contract amount or by entering an actual $ amount allocated for each phase (click the appropriate button in Set Budget By). You can also choose to set the allocated time either by hours or $/Hr. This allows you to budget the amount of hours budgeted for each phase or the anticipated average dollar per hour. Therefore the budget can be set by 4 methods:

    Choosing the appropriate budget method will open the corresponding column to enter budget values.

Please note the budget totals accumulate at the bottom of the project phases.